  • Update: Lakeview Ditch Rehabilitation Project

    CBLCA

    June 22, 2026
    Transportation, Transit and Infrastructure
    Update: Lakeview Ditch Rehabilitation Project

    In case you missed it in the Bay Ward newsletter on May 29, plans have changed for the Lakeview Ditch Rehabilitation Project. Due to budget constraints, the project will now be phased into two tender packages:

    Tender package 1 (Storm sewer replacement on Holly Acres Road, from Carling Avenue to Aero Drive):

    • Design completion: summer 2026
    • Construction start: fall 2026
    • Construction completion: early 2027

    Tender package 2 (Ditch rehabilitation work in Lakeview Community and new sidewalk if feasible):

    • Design completion: fall 2026
    • Construction start: spring 2027
    • Construction completion: fall 2028

    We had expected a second public information session this spring, but it is now expected to take place fall 2026. Councillor Kavanagh has said that her office will share the date and details for that session when they are confirmed. 

    You can find more information about the project, including the presentation from the first public information session on the City website at Lakeview ditch rehabilitation.

    Ditch Rehabilitation, Lakeview Ditches, TIP Transportation Infrastructure and Planning